LawcurbLawcurbTMLegal Intelligence. Simplified.

Hirani Developersv.Nehru Nagar Samruddhi CHS Ltd and Another

Citation:
2026 INSC 484
Date:
13 May 2026
Reading time:
15 min read

Legal Analysis: Hirani Developers vs. Nehru Nagar Samruddhi CHS Ltd. and Another

Citation: 2026 INSC 484
Court: Supreme Court of India
Bench: Justice Sanjay Kumar and Justice K. Vinod Chandran (Division Bench)
Date of Decision: 13th May 2026
Nature of Judgment: Civil Appeals under Article 136 of the Constitution of India against the common order of the Bombay High Court rejecting applications under Section 11 of the Arbitration and Conciliation Act, 1996.


Synopsis of the Judgment

The appellant (developer) entered into a Development Agreement with a cooperative housing society, which contained an arbitration clause (Clause 36). Subsequently, the appellant entered into separate Permanent Alternate Accommodation Agreements with individual members of the society. These later agreements contained Clause 14, which stated that “all the terms and conditions of the Development Agreement dated 04/07/2012 shall be construed to form a part of these presents and all the clauses of the same shall be binding on the parties hereto.” Disputes arose, and the appellant invoked arbitration. The High Court rejected the Section 11 applications, holding that the individual members were not privy to the arbitration clause in the Development Agreement and that a mere generic reference was insufficient to incorporate the arbitration clause. The Supreme Court reversed, holding that Clause 14 was not a mere reference but a clear incorporation of the entire Development Agreement (including the arbitration clause) into the later agreements. The Court appointed a sole arbitrator.


1. Basic Information of the Judgment

  • Case Title: Hirani Developers vs. Nehru Nagar Samruddhi CHS Ltd. and Another (with connected matters)

  • Civil Appeal Nos.: Arising out of SLP(C) Nos. 38407-38411 of 2025

  • Bench: Justice Sanjay Kumar and Justice K. Vinod Chandran (Division Bench)

  • Date of Decision: May 2026 (exact date not specified)

  • Citation: 2026 INSC 484

  • Appeal From: Common order dated 26.06.2025 of the High Court of Judicature at Bombay in Arbitration Applications (not specified)


2. Legal Framework

Laws and Provisions Involved

  • Arbitration and Conciliation Act, 1996: Section 7 (arbitration agreement), Section 7(5) (reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the reference makes that clause part of the contract), Section 11 (appointment of arbitrator)

  • Indian Contract Act, 1872: Principles of incorporation of terms by reference

Key Precedents Cited

  1. M.R. Engineers and Contractors Private Limited v. Som Datt Builders Limited (2009) 7 SCC 696 – Distinguished between “mere reference” to a document and “incorporation” of a document by reference; held that if a contract provides that the referred document shall form part and parcel of the contract, then the entire document (including arbitration clause) gets incorporated; mere reference for a limited purpose does not incorporate the arbitration clause.

  2. NBCC (India) Limited v. Zillion Infraprojects Private Limited (2022) (citation not fully specified) – An arbitration clause in another document gets incorporated into a later contract if the contract contains a clear reference to the document containing the arbitration clause and such reference clearly indicates the intention to incorporate the arbitration clause.

What the Judgment is About

The judgment deals with the doctrine of incorporation of an arbitration clause by reference under Section 7(5) of the Arbitration Act. It clarifies the distinction between a “mere reference” (where only specific parts of a document are adopted) and “incorporation” (where the entire document is bodily lifted into the later contract). The Court holds that when a later agreement states that all terms and conditions of an earlier agreement shall form part of the later agreement and that all clauses of the earlier agreement shall be binding on the parties, the arbitration clause from the earlier agreement stands incorporated, even if the later agreement does not itself contain a separate arbitration clause.


3. Relevant Facts

  • Development Agreement (20.12.2011, registered 04.07.2012): The appellant (Hirani Developers) entered into a Development Agreement with respondent No. 1 (Nehru Nagar Samruddhi CHS Ltd.) for redevelopment of a dilapidated project. Clause 36 of this agreement contained an arbitration clause: “In case of any dispute or differences arose in respect of the terms and conditions of said agreement, both parties shall appoint sole Arbitrator and said Arbitration proceedings shall be conducted under the provisions of Arbitration and Conciliation Act, 1996.”

  • Permanent Alternate Accommodation Agreements (02.09.2023 and 12.01.2024): The appellant executed separate agreements with individual members of the society (respondents herein) – Narayan Haldankar, Malan Valkunde, Ravindra Walanju, Pradeep Govekar and Suchita Pawar. All these agreements contained Clause 14, which read: “It is clarified that all the terms and conditions of the Development Agreement dated 04/07/2012 shall be construed to form a part of these presents and all the clauses of the same shall be binding on the parties hereto.”

  • Dispute and invocation: The respondent members filed complaints against the appellant under the Consumer Protection Act, 2019. The appellant issued legal notices dated 28.02.2025 under Section 21 of the Arbitration Act, invoking Clause 36 of the Development Agreement and proposing arbitration. The members refused, stating they had approached the Consumer Commission.

  • Section 11 applications before Bombay High Court: The appellant filed five applications under Section 11 seeking appointment of an arbitrator. The High Court dismissed them on the ground that there was no arbitration clause in the Permanent Alternate Accommodation Agreements and that the members were not privy to the Development Agreement.

  • Supreme Court appeal: The appellant appealed.


4. Issues

  1. Whether Clause 14 of the Permanent Alternate Accommodation Agreements operates to incorporate the arbitration clause (Clause 36) from the Development Agreement into those later agreements, thereby creating an arbitration agreement between the appellant and the individual member respondents.

  2. Whether the High Court erred in holding that a mere reference to an earlier document is insufficient to incorporate an arbitration clause, and whether the principles laid down in M.R. Engineers and NBCC (India) Ltd. were correctly applied.


5. Ratio Decidendi

A. Distinction between “mere reference” and “incorporation” (Paras 9-11):

The Court, relying on M.R. Engineers, explained that a mere reference to another document (e.g., for specifications or payment terms) does not incorporate the entire document. However, when a contract states that the referred document shall “form part and parcel” of the contract, or that “all terms and conditions” of the referred document shall be read as part of the contract, or that the contract will be “governed by the provisions” of the referred document, then the entire document (including any arbitration clause) gets bodily lifted and incorporated.

B. Clause 14 – clear intention to incorporate entire Development Agreement (Paras 11-12):

Clause 14 of the Permanent Alternate Accommodation Agreements provided: “all the terms and conditions of the Development Agreement … shall be construed to form a part of these presents and all the clauses of the same shall be binding on the parties hereto.” This is not a mere reference for a limited purpose. It unequivocally indicates the intention of the parties to import the Development Agreement “body and soul” into the later agreements. Therefore, Clause 36 (arbitration clause) stands incorporated.

C. Application of Section 7(5) of the Arbitration Act (Para 8-10):

Section 7(5) provides that a reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference makes that arbitration clause part of the contract. The Court held that the reference in Clause 14 satisfies this requirement. The High Court’s conclusion that Section 7(5) was not satisfied was erroneous.

D. Rejection of the “privity” argument (implicitly):

The High Court had held that the members of the society were not privy to the arbitration clause in the Development Agreement. The Supreme Court, by holding that the arbitration clause was incorporated into the later agreements to which the members were parties, implicitly rejected that argument. The members voluntarily agreed to Clause 14, thereby making the arbitration clause binding on them.

E. Appointment of arbitrator (Para 13):

Since the Court found that an arbitration agreement existed, it exercised its power under Section 11(6) to appoint a sole arbitrator (Mr. Vishal Kanade, Advocate).


6. New Legal Principles Established / Reiterated

  • Clear incorporation language in a contract is sufficient to incorporate an arbitration clause from an earlier document. Specific phrases such as “all the terms and conditions of the earlier agreement shall form part of this agreement” or “all clauses of the earlier agreement shall be binding” are sufficient to import an arbitration clause into the later contract, even if the later contract does not separately mention arbitration.

  • The fact that the parties to the later contract are different from the parties to the earlier contract does not bar incorporation, as long as the later contract clearly expresses the intention to be bound by the terms of the earlier document. The later parties become bound by the incorporated clause by their own agreement.

  • This judgment clarifies the application of M.R. Engineers and NBCC: The test is not whether the later agreement contains a separate arbitration clause, but whether the intention to incorporate the earlier document (including its arbitration clause) is clearly expressed.


7. Court’s Analysis and Examination of Concepts

The Court first noted the facts and the conflicting clauses. It then examined the language of Clause 14. It contrasted this language with the examples given in M.R. Engineers of mere reference (e.g., “the specifications will be as provided in an earlier contract”). The Court observed that Clause 14 did not limit incorporation to specific portions; it used the phrase “all the terms and conditions” and “all the clauses”. This is a classic case of “incorporation” (bodily lifting) rather than “reference”.

The Court also noted that the High Court had erroneously held that Section 7(5) was not satisfied. The High Court’s reasoning (that a mere generic reference is insufficient) was correct in law, but the facts of the case fell under the exception – where the reference is not generic but specific and all‑encompassing.

The Court did not discuss the respondent’s argument that the members were not privy to the Development Agreement. By holding that the arbitration clause was incorporated into the later agreements, the Court effectively held that the members became privy to that clause by their own consent in the later agreements.

The Court then exercised its power under Section 11(6) to appoint an arbitrator, as there was no dispute that the parties were ad idem on the existence of an arbitration agreement (the dispute was only about its existence, which the Court resolved).


8. Critical Analysis

Strengths: The judgment correctly applies the settled law on incorporation of arbitration clauses. It provides a clear, practical test: if the later contract uses language that indicates a wholesale adoption of the earlier document (“all terms and conditions”, “all clauses shall be binding”), the arbitration clause is incorporated. This prevents parties from evading arbitration by artificially splitting agreements into a “main” agreement and “subsequent” agreements. The judgment also respects party autonomy – the individual members agreed to Clause 14, so they cannot later claim that they are not bound by the arbitration clause.

Potential concerns: The judgment does not address the scenario where the later contract is between the developer and individual members, but the earlier Development Agreement was between the developer and the society. The Court assumed that the members had the authority to bind themselves by reference to a document to which they were not originally parties. However, by signing the later agreement with Clause 14, they voluntarily subjected themselves to the terms of the Development Agreement. This is a standard principle of contract law – a person can agree to be bound by the terms of a document they have not previously seen, as long as the reference is clear and they have notice. The judgment is sound.

Practical impact: This judgment will be cited in real estate development disputes where the developer has a master agreement with a society (containing an arbitration clause) and later executes individual agreements with members. It will also be used in other commercial contexts (franchise agreements, supply chain contracts) where an earlier master agreement is incorporated by reference into later agreements. It provides a clear drafting guideline: to incorporate an arbitration clause, use unequivocal language such as “all terms and conditions of the earlier agreement shall form part of this agreement.”


9. Final Outcome

  • Civil Appeals allowed.

  • The common order dated 26.06.2025 of the Bombay High Court is set aside.

  • It is held that there exists a valid arbitration agreement between the appellant and each of the five respondent members by incorporation of Clause 36 of the Development Agreement into the Permanent Alternate Accommodation Agreements.

  • Mr. Vishal Kanade, Advocate (address provided) is appointed as the Sole Arbitrator to adjudicate the disputes between the parties.

  • The learned Arbitrator shall make his declaration under Section 12 of the Arbitration Act within fifteen days from the receipt of a copy of this order.

  • The Arbitrator shall be entitled to fees in terms of the Fourth Schedule to the Arbitration Act.

  • No order as to costs.

  • Pending applications disposed of.


10. Practical Application (Use in Court)

  • For developers/claimants (seeking arbitration): If you have executed a master agreement (e.g., with a society or association) that contains an arbitration clause, and subsequently execute individual agreements with members that incorporate the master agreement by reference (using language like “all terms and conditions of the master agreement shall form part of this agreement”), you can successfully invoke arbitration against the individual members. Cite this judgment to argue that the arbitration clause is incorporated.

  • For individual members/respondents (opposing arbitration): If the later agreement uses a general reference (e.g., “the terms of the earlier agreement shall apply to the extent relevant”), argue that it is a “mere reference” and not an “incorporation”. Also, if the later agreement is silent on arbitration, you may still be bound if the incorporation language is clear. After this judgment, the focus will be on the precise wording of the incorporation clause.

  • For courts (under Section 11): When examining whether an arbitration clause from an earlier document is incorporated into a later document, examine the language of the later document. If it says “all terms and conditions of the earlier document shall form part of this contract” or similar, find that the arbitration clause is incorporated. If it merely refers to the earlier document for a specific purpose (e.g., “specifications as per the earlier contract”), find that it is a mere reference and not incorporation.


11. Court Lines

“There is a difference between reference to another document in a contract and incorporation of another document in a contract, by reference. In the first case, the parties intend to adopt only specific portions or part of the referred document for the purposes of the contract. In the second case, the parties intend to incorporate the referred document in entirety, into the contract.” (Para 9, quoting M.R. Engineers)

“If a contract refers to a document and provides that the said document shall form part and parcel of the contract, or that all terms and conditions of the said document shall be read or treated as a part of the contract, or that the contract will be governed by the provisions of the said document, or that the terms and conditions of the said document shall be incorporated into the contract, the terms and conditions of the document in entirety will get bodily lifted and incorporated into the contract.” (Para 9, quoting M.R. Engineers)

“This was, thus, not a case of mere reference to an earlier agreement but a case where the parties to the later contract clearly intended to import the Development Agreement, body and soul, into the later agreements. Therefore, there can be no doubt as to the incorporation of Clause 36 of the Development Agreement, i.e., the arbitration clause, into the Permanent Alternate Accommodation Agreements.” (Para 12)


12. Legal Strategy Insight

  • For the appellant (developer): When drafting the Permanent Alternate Accommodation Agreements, ensure that the incorporation clause is explicit and unambiguous. Use phrases like “all the terms and conditions of the Development Agreement dated … shall form part of this agreement” and “all clauses of the said Development Agreement shall be binding on the parties hereto.” Avoid vague language like “the terms of the Development Agreement shall apply” without specifying “all” terms. If the respondent members later deny arbitration, file a Section 11 application and rely on this judgment to argue that the arbitration clause is incorporated.

  • For the respondent members (individuals): Before signing any agreement that incorporates a prior document by reference, read the prior document carefully. If you do not wish to be bound by its arbitration clause, insist on a separate, stand‑alone agreement without incorporation or with an express exclusion of the arbitration clause. If you have already signed, argue that the incorporation clause is ambiguous or that it was a mere reference for limited purposes (e.g., only for construction specifications, not for dispute resolution). However, after this judgment, such arguments will succeed only if the language is genuinely limited.

  • For courts: When interpreting a contract that refers to an earlier document, first determine whether the reference is for a limited purpose or for wholesale incorporation. Look for keywords: “all terms and conditions”, “shall form part”, “shall be binding” indicate incorporation. “Shall be as per”, “as provided in” indicate mere reference. Apply the principles from M.R. Engineers and this judgment to give effect to party autonomy.